SEWAGE TREATMENT PLANT OF MARINES (95), ECO-BUILDING OF CONSTRUCTED WETLANDS

This project was presented as part of a lecture done by Architect Ruba Alabed at Chamber of Commerce and Industry in Versailles - 2008

Client : City of Marines
Location : Marines (95)
Project : Construction of wetlands
Mission : Landscaping
Consultant Designer : AR ARCHITECTES
Area : 1 600 m²
Cost : 7 800 K € (plant + wetlands)
Date : End of construction March 2009

This plant is designed in accordance with the HEQ® standards: Zero visual pollution, Zero smell and noise pollution. During the design phase, all types of pollutions were kept at a low level using technical precautions that ensure comfort for on-site workers and surrounding residents. 1600 m² of constructed wetlands have been designed and executed to treat a flow 376m3 per day.