Lycée Isaac Newton à Clichy (92)

Technical Refurbishment of Isaac Newton High School in Clichy - France

Client : Île-de-France Construction Durable

Location : Région Île-de-France

Project : Project management, Sanitary plan and director diagram

Consultant : AR ARCHITECTES, VERDI, CITYACCESS, SI PREV

Area : 10 000m²

Cost : Sanitary plan : 400 000€, Director diagram : 1 500 000€

Date : Sanitary plan : end of work 2021, Director diagram : detailed design in progress

The Isaac Newton high school must meet the new rules and regulations in matter of refurbishment, security and accessibility. Thus, three missions are necessary. The director diagram consists of bringing the high school’s fire safety system back to conformity. The sanitary plan aim to bring all of the school’s sanitary facilities up to actual standards. Finally, another mission of accessibility for disabled people and fire exit security are as well brought up to actual regulations.